blog

Works Performed

Steel Installation: 19,750 Tons
Sandwich Panel Installion: 57,500 m²
Pipe Installation: 152,500 WDI
Lub - Oil Pipe Installation: 4,500 m
Sand Blasting & Painting: 123,000 m²
Rezervoir Sand Blasting & Painting: 16,500 m²
 

Project Description

Udokan Mining and Metallurgical Plant will produce copper cathodes and sulfide concentrate. The first stage of the plant will deliver up to 135 thousand tonnes of copper per year. Udokan ores will be processed using a unique flotation and hydrometallurgy scheme.


Total Number of Personnel

403