Works Performed

Pipe Installation: 75.000 WDI
Steel Erection: 3.750 TON
Touch-Up: 6.000 m2
Insulation: 40.000 m2
Electrical Heat Tracing: 30.000 m
Scaffolding Assembly/Dismantling: 20.000 m2
 

Project Description

Construction of mechanical works within the scope of UST-LUGA Gas Processing Plant Project.
 

Total Number of Personnel

1100