blog

Works Performed

Steel Erection: 6,000 Tons
Pipe Installation: 220,000 WDI
Workshop Sand Blasting & Painting: 650,000 m²
Touch-up Painting & Labelling: 600,000 mh
Reservoir Blasting & Painting: 43 pcs, 75,000 m²
Fire Proof Painting: 6,000 m²
E&I Erection: 350,000 m
 

Project Description

AGPP will be one of the largest gas processing plants in the world with a feed gas capacity of 42 billion cubic meters of natural gas per year, and will be an essential part of Gazprom’s strategic plan to supply Russian natural gas to China. The AGPP Complex will be only the first milestone of a large industrial development, that will include significant investments of the Russian Federation in downstream petrochemicals to be fed with products associated to natural gas of AGPP.
 

Total Number of Personnel

1100