Works Performed

Sand Blasting & Painting: 330,000 m²
Pipe Touch-up: 15,500 m
Steel Touch-up: 140,000 m²
Steel Fire Proof Painting (PFP): 1,500 m²
Equipment Fire Proof Painting: 1,000 m²
Pipe Installation: 2,000 WDI
 

Project Description

The project includes the construction of three LNG trains, with a capacity of 6.6 mtpa of LNG each. The total LNG capacity of the three trains will be 19.8 mtpa and about 1.6 mtpa of stable gas condensate. The project employs an innovative construction concept using gravity-based structures (GBS).
 

Total Number of Personnel

275